Check list for examination of Procurement (Works/ Purchases/ Services) Contracts
|
|
I. Pre-Award Stage
|
|
1. Financial and Technical sanction of competent authority is available.
|
|
2. Adequate and wide publicity is given. Advertisement is posted on website and |
|
tender documents are available for downloading.
|
|
3. Convenient tender receiving/opening time and address of the tender receiving |
|
officials/tender box are properly notified.
|
|
4. In the case of limited tender, panel is prepared in a transparent manner |
|
clearly publishing the eligibility criteria. The panel is updated regularly.
|
|
5. Pre-qualification criteria are properly defined/ notified.
|
|
6. Short listed firms/consultants are fulfilling the eligibility criteria. There is no |
|
deviation from notified criteria during evaluation.
|
|
7. Experience certificates submitted have been duly verified.
|
|
8. Tenders/bids are opened in the presence of bidders.
|
|
9. Corrections/omissions/additions etc., in price bid are properly numbered and |
|
attested and accounted page –wise. Tender summary note/ Tender opening |
|
register is scrupulously maintained.
|
|
10. Conditions having financial implications are not altered after opening of the |
|
price bids.
|
|
11. In case of consultancy contracts (a)Upper ceiling limit is fixed for consultancy |
|
fee and (b) Separate rates for repetitive works are fixed.
|
|
B. Post-award stage
|
|
(a) General
|
|
1. Agreement is complete with all relevant papers such as pre-bid conference |
|
minutes, etc.
|
|
2. Agreement is page-numbered, signed and sealed properly.
|
|
3. Bank Guarantee is verified from issuing bank.
|
|
4. Insurance policies, labour licence, performance guarantee are taken as per |
|
contract.
|
|
5. Technical personnel are deployed as per contract.
|
|
6. Plant and equipment are deployed as per contract.
|
|
7. Action for levy of liquidated damages is taken in case of delay/default.
|
|
(b) Payments to contractors
|
|
1. Price escalation is paid only as per contract.
|
|
2. Retention Money/Security Deposit is deducted as per contract.
|
|
3. Recovery of Mobilisation & Equipment advance is made as per the provisions |
|
in the contract.
|
|
4. Recovery of I.Tax & Works Contract tax is made as per provisions in the |
|
contract.
|
|
5. Glaring deviations are supported with adequate justification and are not |
|
advantageous to the contractor.
|
|
(c) Site Records
|
|
1. Proper system of recording and compliance of the instructions issued to the |
|
contractors is maintained.
|
|
2. Proper record of hindrances is maintained for the purpose of timely removal |
|
of the hindrance and action for levy of liquidated damages.
|
|
3. Mandatory tests are carried out as per the frequency prescribed in the Agreement. |